|
ContID 262011 EST NO 0005 |
Date:07/16/2026 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
| Contract ID | 262011 | Estimate Number | 0005 | Estimate Type | DRAFT_PROGRESS | ||
| District Office | MANCHESTER (11320) Perkins, Robert W. | ||||||
| Contractor | REYNOLDS-CENTRAL SEAL A JOINT VENTURE | MARS ADDR SN 0 | |||||
| PO BOX 1558 | |||||||
| BOWLING GREEN , KY , 42102 | |||||||
| Pay Period | 07/01/2026 TO 07/12/2026 | ||||||
| Date Approved | 07/14/2026 | ||||||
| Primary Proj Number | MP12100002611 | ||||||
| Project No. | FE01 121 DW26 000011 | ||||||
| Primary County | VARIOUS | ||||||
| Name of Road | VARIOUS ROUTES IN DISTRICT 11 (& 10 PERRY COUNTY KY 484) | ||||||
| Description | VARIOUS ROUTES IN DISTRICTS 10 & 11 | ||||||
| Date Let | 01/29/2026 | Formal Acceptance | |||||
| Date Awarded | 02/10/2026 | Date Work Began | 05/12/2026 | ||||
| Date Contract Executed | 02/12/2026 | Open To Traffic | |||||
| Date NTP Issued | 03/09/2026 | Actual Completion Date | |||||
| Current Contract Amount | $2,939,000.00 |
Total to Date |
Prev to Date |
This Estimate |
||
| Original Amount | $2,939,000.00 |
Total Earnings | $1,244,871.55 |
$1,153,138.35 |
$91,733.20 |
|
| Percent Complete | 42.36 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
| Funds Available | $1,694,128.45 |
Gross Earnings | $1,244,871.55 |
$1,153,138.35 |
$0.00 |
|
| Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
| TOTAL | $1,244,871.55 |
$1,153,138.35 |
91,733.20 |
|||
| Contract Id | 262011 | Change Order Summary |
County | VARIOUS | ||||||
| Estimate Nbr | 0005 | Project Number | FE01 121 DW26 000011 | |||||||
| Contractor | REYNOLDS-CENTRAL SEAL A JOINT VENTURE | Period | 07/01/2026 TO 07/12/2026 | |||||||
| CHANGE ORDERS HISTORY | ||||||||||
| CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
| Contract Adjustments |
|
|
| Adjustment Description | Est No |
Adjustment Amount |
| Line Item Adjustments History | |||||||||
| PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
||
| Contract Id | 262011 | COMMONWEALTH OF KENTUCKY |
County | VARIOUS | ||||||
| Contract Type | TRWB WATERBOURNE PAINT STRIPING | TRANSPORTATION CABINET |
Primary Project Number | MP12100002611 | ||||||
| Estimate Nbr | 0005 | Period | 07/01/2026 TO 07/12/2026 | |||||||
| Contractor | REYNOLDS-CENTRAL SEAL A JOINT VENTURE | |||||||||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | ||||||||
| LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0000 ROADWAY | |||||||
| 0005 | QUALITY CONTROL | 02572 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 40,000.00 | 0.00 | |||
| 0010 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.500 | 0.500 | 60,000.00 | 30,000.00 | |||
| 0015 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 50.00 | 50.000 | 0.000 | 0.000 | 105.00 | 0.00 | |||
| 0020 | WATER BLASTING EXISTING STRIPE | 22664EN | LF | 500.00 | 500.000 | 0.000 | 0.000 | 3.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0007 BELL COUNTY RURAL SECONDARY ROUTES | |||||||
| 0025 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES BELL 50% INITIAL | 06520 | MILE | 20.88 | 20.884 | 16.596 | 16.596 | 235.00 | 3,900.06 | |||
| 0027 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES BELL 50% FINAL | 06520 | MILE | 20.88 | 20.884 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0030 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES BELL 50% INITIAL | 06521 | MILE | 169.43 | 169.438 | 150.141 | 150.141 | 245.00 | 36,784.54 | |||
| 0032 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES BELL 50% FINAL | 06521 | MILE | 169.43 | 169.438 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0026 CLAY COUNTY RURAL SECONDARY ROUTES | |||||||
| 0035 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CLAY 50% INITIAL | 06520 | MILE | 13.67 | 13.676 | 14.261 | 14.261 | 235.00 | 3,351.33 | |||
| 0037 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CLAY 50% FINAL | 06520 | MILE | 13.67 | 13.676 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0040 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CLAY 50% INITIAL | 06521 | MILE | 202.26 | 202.261 | 201.223 | 201.223 | 245.00 | 49,299.63 | |||
| 0042 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CLAY 50% FINAL | 06521 | MILE | 202.26 | 202.261 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0048 HARLAN COUNTY RURAL SECONDARY ROUTES | |||||||
| 0045 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES HARLAN 50% INITIAL | 06520 | MILE | 116.13 | 116.136 | 15.115 | 111.262 | 126.377 | 235.00 | 3,552.02 | 29,698.59 | |
| 0047 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES HARLAN 50% FINAL | 06520 | MILE | 116.13 | 116.136 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0050 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES HARLAN 50% INITIAL | 06521 | MILE | 185.58 | 185.582 | 24.806 | 155.202 | 180.008 | 245.00 | 6,077.47 | 44,101.96 | |
| 0052 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES HARLAN 50% FINAL | 06521 | MILE | 185.58 | 185.582 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0055 JACKSON COUNTY RURAL SECONDARY ROUTES | |||||||
| 0055 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES JACKSON 50% INITIAL | 06521 | MILE | 183.89 | 183.890 | 180.555 | 180.555 | 245.00 | 44,235.97 | |||
| 0057 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES JACKSON 50% FINAL | 06521 | MILE | 183.89 | 183.890 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0061 KNOX COUNTY RURAL SECONDARY ROUTES | |||||||
| 0060 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES KNOX 50% INITIAL | 06520 | MILE | 24.38 | 24.381 | 23.941 | 23.941 | 235.00 | 5,626.13 | |||
| 0062 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES KNOX 50% FINAL | 06520 | MILE | 24.38 | 24.381 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0065 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES KNOX 50% INITIAL | 06521 | MILE | 172.09 | 172.091 | 174.695 | 174.695 | 245.00 | 42,800.27 | |||
| 0067 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES KNOX 50% FINAL | 06521 | MILE | 172.09 | 172.091 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| 0070 | PAVE STRIPING-WB PAINT-6 IN Y RS ROUTES KNOX 50% INITIAL | 06523 | MILE | 18.94 | 18.949 | 24.339 | 24.339 | 365.00 | 8,883.73 | |||
| 0072 | PAVE STRIPING-WB PAINT-6 IN Y RS ROUTES KNOX 50% FINAL | 06523 | MILE | 18.94 | 18.949 | 0.000 | 0.000 | 365.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0063 LAUREL COUNTY RURAL SECONDARY ROUTES | |||||||
| 0075 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LAUREL 50% INITIAL | 06520 | MILE | 2.07 | 2.076 | 2.047 | 2.047 | 235.00 | 481.04 | |||
| 0077 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LAUREL 50% FINAL | 06520 | MILE | 2.07 | 2.076 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0080 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LAUREL 50% INITIAL | 06521 | MILE | 212.90 | 212.900 | 203.788 | 203.788 | 245.00 | 49,928.06 | |||
| 0082 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LAUREL 50% FINAL | 06521 | MILE | 212.90 | 212.900 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0066 LESLIE COUNTY RURAL SECONDARY ROUTES | |||||||
| 0085 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LESLIE 50% INITIAL | 06520 | MILE | 32.62 | 32.622 | 26.546 | 26.546 | 235.00 | 6,238.31 | |||
| 0087 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LESLIE 50% FINAL | 06520 | MILE | 32.62 | 32.622 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0090 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LESLIE 50% INITIAL | 06521 | MILE | 136.56 | 136.562 | 91.392 | 91.392 | 245.00 | 22,391.04 | |||
| 0092 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LESLIE 50% FINAL | 06521 | MILE | 136.56 | 136.562 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0097 PERRY COUNTY RURAL SECONDARY ROUTES | |||||||
| 0095 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES PERRY 50% INITIAL | 06521 | MILE | 1.48 | 1.480 | 35.731 | 35.731 | 245.00 | 8,754.09 | |||
| 0097 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES PERRY 50% FINAL | 06521 | MILE | 1.48 | 1.480 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0118 WHITLEY COUNTY RURAL SECONDARY ROUTES | |||||||
| 0100 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES WHITLEY 50% INITIAL | 06520 | MILE | 0.63 | 0.638 | 0.698 | 0.698 | 235.00 | 164.03 | |||
| 0102 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES WHITLEY 50% FINAL | 06520 | MILE | 0.63 | 0.638 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0105 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES WHITLEY 50% INITIAL | 06521 | MILE | 173.73 | 173.738 | 169.475 | 169.475 | 245.00 | 41,521.37 | |||
| 0107 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES WHITLEY 50% FINAL | 06521 | MILE | 173.73 | 173.738 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| 0110 | PAVE STRIPING-WB PAINT-6 IN Y RS ROUTES WHITLEY 50% INITIAL | 06523 | MILE | 16.05 | 16.056 | 8.590 | 8.590 | 365.00 | 3,135.35 | |||
| 0112 | PAVE STRIPING-WB PAINT-6 IN Y RS ROUTES WHITLEY 50% FINAL | 06523 | MILE | 16.05 | 16.056 | 0.000 | 0.000 | 365.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0121 MP ROUTES - DISTRICT 11 | |||||||
| 0115 | PAVE STRIPING-WB PAINT-4 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06520 | MILE | 689.03 | 689.030 | 558.804 | 558.804 | 235.00 | 131,318.94 | |||
| 0117 | PAVE STRIPING-WB PAINT-4 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06520 | MILE | 689.03 | 689.030 | 0.000 | 0.000 | 235.00 | 0.00 | |||
| 0120 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06521 | MILE | 887.90 | 887.909 | 14.860 | 733.366 | 748.226 | 245.00 | 3,640.70 | 183,315.37 | |
| 0122 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06521 | MILE | 887.90 | 887.909 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| 0125 | PAVE STRIPING-WB PAINT-6 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06522 | MILE | 220.55 | 220.550 | 246.070 | 246.070 | 335.00 | 82,433.45 | |||
| 0127 | PAVE STRIPING-WB PAINT-6 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06522 | MILE | 220.55 | 220.550 | 0.000 | 0.000 | 335.00 | 0.00 | |||
| 0130 | PAVE STRIPING-WB PAINT-6 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06523 | MILE | 253.40 | 253.403 | 294.689 | 294.689 | 365.00 | 107,561.48 | |||
| 0132 | PAVE STRIPING-WB PAINT-6 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06523 | MILE | 253.40 | 253.403 | 0.000 | 0.000 | 365.00 | 0.00 | |||
| 0135 | DURABLE WATERBORNE MARKING-6 IN W INTERSTATE, PARKWAY& STATE PRIMARY RTS VARIOUS 50% INITIAL | 23140EN | MILE | 449.16 | 449.169 | 140.239 | 174.645 | 314.884 | 500.00 | 70,119.50 | 157,442.00 | |
| 0137 | DURABLE WATERBORNE MARKING-6 IN W INTERSTATE, PARKWAY& STATE PRIMARY RTS VARIOUS 50% FINAL | 23140EN | MILE | 449.16 | 449.169 | 0.000 | 0.000 | 500.00 | 0.00 | |||
| 0140 | DURABLE WATERBORNE MARKING-6 IN Y INTERSTATE, PARKWAY& STATE PRIMARY RTS VARIOUS 50% INITIAL | 23141EN | MILE | 376.96 | 376.967 | 15.170 | 260.293 | 275.463 | 550.00 | 8,343.50 | 151,504.65 | |
| 0142 | DURABLE WATERBORNE MARKING-6 IN Y INTERSTATE, PARKWAY& STATE PRIMARY RTS VARIOUS 50% FINAL | 23141EN | MILE | 376.96 | 376.967 | 0.000 | 0.000 | 550.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0122 MP ROUTES - DISTRICT 10 | |||||||
| 0145 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY&SUPPLEMENTAL ROUTES VARIOUS D10 50% INITIAL | 06521 | MILE | 7.31 | 7.314 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| 0147 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY&SUPPLEMENTAL ROUTES VARIOUS D10 50% FINAL | 06521 | MILE | 7.31 | 7.314 | 0.000 | 0.000 | 245.00 | 0.00 | |||
| Project | MP12100002611 | Fed/State Project Number | FE01 121 DW26 000011 | Category | 0123 DEMOBILIZATION | |||||||
| 0150 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 44,121.90 | 0.00 | |||
| SUBTOT | $91,733.19 |
$1,244,871.450 |
||||||||||
| LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
| SUBTOT | 0.00 |
$0.000 |
||||||||||